Progress Milestones

2014

March
  • 11th Street Inbound Freeway Bridge opens third lane to ramp connecting to Interstate 695 and Southeast-Southwest Freeway
  • South Capitol Street Corridor Segments 1 and 2 draft Request for Proposals (RFP) issued to four short-listed design-build contractor firms
February
  • AWI Transportation Master Plan 2014 Update published
  • New eastbound ramp to 11th Street Outbound Freeway Bridge from the Southeast-Southwest Freeway Opens
January
  • South Capitol Street Corridor Segments 1 and 2 notification of four short-listed design-build contractor firms

2013

December
  • Anacostia Riverwalk Trail Kenilworth Aquatic Segment construction contract awarded
September
  • New Local 11th Street Bridge officially opened and dedicated as 11th Street Officer Kevin J. Welsh Memorial Bridge
August
  • South Capitol Street Corridor Segments 1 and 2 design-build contractor Statements of Qualifications (SOQs) received
July
  • Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment advertised for construction
June
  • 11th Street Bridge Project Phase 1 construction substantially completed
May
  • Second of two new Anacostia Riverwalk Trail fiberglass-decked bridges over CSX railroad tracks completed
January
  • Pennsylvania and Potomac Avenue SE Intersection and Barney Circle-Southeast Boulevard Project environmental planning studies begun

2012

December
  • New outbound ramp between I-695 outbound and northbound DC-295 opened to traffic
  • Final report for the M Street SE/SW Transportation Study published
  • Design for the new Frederick Douglass Memorial Bridge unveiled
November
  • Pennsylvania-Potomac Avenue Intersection and Barney Circle-Southeast Boulevard Projects environmental planning studies launched
October
  • New ramp from local 11th Street Bridge to southbound I-295 opened to traffic
  • Design of Kenilworth Gardens Segment of the Anacostia Riverwalk Trail unveiled
September
  • 11th Street Bridge Project started Project Completion Phase (Phase 2)
July
  • Kenilworth Gardens Segment of the Anacostia Riverwalk Trail final planning milestone achieved with Finding of No Significant Impact (FONSI) issued
  • New ramp from southbound DC-295 to Inbound 11th Street Freeway Bridge and I-395 opened to traffic
June
  • Kenilworth Aquatic Gardens Segment of the Anacostia Riverwalk Trail awarded $10 million TIGER Grant by U.S. Department of Transportation for construction
March
  • New Maine Avenue section of the Anacostia Riverwalk Trail completed
January
  • New 11th Street Bridge Project Outbound Freeway Bridge opened
  • South Capitol Street Corridor Project Section 106 and 4(f) documents signed
  • South Capitol Street Corridor Project Preliminary Engineering began
  • South Capitol Street Corridor Project land acquisition began

2011

December
  • New 11th Street Bridge Project Inbound Freeway Bridge opened
August
  • Anacostia Park segment of the Anacostia Riverwalk Trail opened
July
  • First section of 11th Street Bridge Project opened with the new elevated section of southbound DC-295/I-295
March
  • South Capitol Street Corridor Project Final Environmental Impact Statement signed

2010

September
  • Yards Park section of Anacostia Riverwalk Trail opened

2009

December
  • 11th Street Bridge Project construction began
Fall
  • Anacostia Riverwalk Trail bridges construction began
Summer
  • First water taxi carried baseball fans from Alexandria to Nationals Park
Spring
  • District Department of Transportation (DDOT) awarded largest contract in its history — 11th Street Bridge Project

2008

Winter
  • Ridership at Anacostia, Navy Yard and Southeast Waterfront Metrorail stations increased by 40 percent over 2003 levels, coinciding with economic growth
Summer
  • 11th Street Bridge Project formally approved and earned Federal Highway Administration Environmental Excellence Award
Spring
  • Frederick Douglass Memorial Bridge rededicated with completion of South Capitol Street near-term improvements
  • Alignment for new Frederick Douglass Memorial Bridge identified

2007

Summer
  • Anacostia Waterfront Initiative (AWI) Transportation Master Plan released
Spring
  • Kenilworth Avenue Corridor Study completed

2005

Fall
  • Anacostia Waterfront Initiative (AWI) Transportation Plan released, identifying transportation improvements to create a world-class waterfront
  • 11th Street Bridges Replacement Study began

2004

Winter
  • South Capitol Street Gateway Corridor and Anacostia Access Study completed

2003

Winter
  • South Capitol Street Corridor Report published by National Capital Planning Commission
Fall
  • Anacostia Waterfront Initiative Framework Plan published
Summer
  • First Anacostia Waterfront Initiative project began with the Anacostia Riverwalk Trail groundbreaking

2000

March
  • Anacostia Waterfront Initiative was born when 19 Federal agencies joined the District in signing a Memorandum of Understanding

Contact Us

Share Your Comments

Share your comments or feedback on the general AWI Program or specific projects.

Contact Us

AWI Email List

Stay Informed

Join our mailing list for the latest news and updates from the AWI Program.

Sign up!

2